Marks & Spencer – Ecclesall Road, Sheffield

Client: Wates Retail
Sub-Contract Value: £330k

Moorhead Excavations were contracted to undertake Site Remediation Works on the above Project for Wates Retail.

The site was a former automotive garage & dealership built on previously landfilled ground.

In accordance with the WSP Environmental Remediation Strategy, and Marks & Spencer’s zero to landfill policy ‘Plan A’, Moorhead Excavations successfully reclaimed, reprocessed and re-used all excavated materials and ground obstructions.

Services Included:

• Concrete slabbing, surface hardstandings and relict foundations were grubbed out and crushed in situ to produce 6F2 for re-use as a site capping layer.

• Hydrocarbon impacted soils were removed to a ‘Soil Hospital’ for bio-remediation and subsequent use as restoration materials.

• 6nr Underground Storage Tanks were purged and waste oils removed for refining. Inert tanks were cold cut and removed for smelting.

• The remaining materials were re-used to make up levels on site or removed for use as colliery restoration soils within a 10km radius.

WHO WE ARE

Some of the best qualified and innovative surveyors and engineers

Learn More

WHAT WE DO

Services for all aspects of Site Preparation and Enabling Works

Learn More

RESPONSIBILITY

Committed to Health & Safety, Quality and the Environment

Learn More
Achilles
Building Confidence
CHAS
ConstrutionLine
NFDC

OUR HIGHLY EXPERIENCED TEAM OUR HERE TO HELP

Contact us today to discuss your next project

GET IN TOUCH
Moorhead Excavations Logo

CALL

0113 279 6556

EMAIL

VISIT

Westfield Court,
Lower Wortley Road,
Leeds, LS12 4PX

LATEST FROM OUR TWITTER FEED