CASE STUDY

Monks Cross Retail Park, York

Client: Caddick Construction
Value: £1.7M

Moorhead Excavations undertook the Site Preparation Works at Monks Cross Retail Park, York for Caddick Construction Ltd.

The site was geotechnically problematic due to the existing ground comprising of soft, silty clays with a high moisture content.

Working with our strategic partner, TR Soil Stabilisation, Moorhead Excavations excavated a series of large on site balancing ponds generating 30,000 cubic metres of fill materials which were treated with lime and cement to make them suitable for engineering to raise the building plateau above the flood risk level. The plateau was stabilised to achieve in excess of 30% CBR providing a stable working platform for following trades.

65,000 square metres of External Hardstandings were then treated in situ to achieve 5% CBR prior to the importing and laying of granular capping and subbase. The full scope of site works carried by Moorhead Excavations.

Services Included:

  • Tree Clearance
  • Pond Draining
  • Asbestos Pick & Disposal
  • Demolition of Outbuildings
  • Soil Strip
  • Pond Formation
  • Bulk Earthworks
  • Soil Stabilisation
  • Stone Import
  • Geotechnical Testing

WHO WE ARE

Some of the best qualified and innovative surveyors and engineers

Learn More

WHAT WE DO

Services for all aspects of Site Preparation and Enabling Works

Learn More

RESPONSIBILITY

Committed to Health & Safety, Quality and the Environment

Learn More
Achilles
Building Confidence
CHAS
ConstrutionLine
NFDC

OUR HIGHLY EXPERIENCED TEAM OUR HERE TO HELP

Contact us today to discuss your next project

GET IN TOUCH
Moorhead Excavations Logo

CALL

0113 279 6556

EMAIL

VISIT

Westfield Court,
Lower Wortley Road,
Leeds, LS12 4PX

LATEST FROM OUR TWITTER FEED